West Kazakhstan Region Launches Major Power Grid Modernization Amid 75% Wear and Outages
Beimbet Musin, head of the West Kazakhstan regional energy and public utilities department, reported on a large-scale power grid upgrade across the region, NewsAsia.kz reports, citing 24.kz.

Beimbet Musin, head of the West Kazakhstan regional energy and public utilities department, reported on a large-scale power grid upgrade across the region, where infrastructure wear had reached 75 percent, NewsAsia.kz reports, citing 24.kz.
Over the past three years, more than 27 billion tenge has been allocated to reconstruct the region's power grids. During this period, specialists replaced over 36,000 poles and more than 8,000 kilometers of lines across 156 settlements. The need for such massive investments arose due to critical infrastructure deterioration, regular failures, and blackouts, which had long remained one of the region's main challenges.
According to Beimbet Musin, three large-scale projects totaling 595 kilometers are currently approved in the region, covering the city of Uralsk and regional districts:
"In West Kazakhstan Region, we have already started reconstructing utility networks, specifically power supply, heating, and wastewater disposal. In 2025, we approved three power grid reconstruction projects worth 10 billion tenge. This covers rural districts and the city of Uralsk. The total length is 595 km. Last year, our grid wear stood at 75%. By the end of the year, we expect grid wear to drop to 68%," he explained.
In addition, 500 million tenge was allocated for routine network maintenance: 370 kilometers of overhead lines were replaced and 70 transformer substations were repaired. As noted by Askar Gaisin, chief engineer of the regional power grid company, sections with the highest number of complaints and accidents were prioritized:
"We first analyzed the areas where emergency outages occurred most frequently, where there were more appeals. The work was completed before the start of the heating season. Furthermore, we have a second investment program. These are also funds built into our tariff. For 640 million tenge, we are repairing 48 kilometers of power grids in Syrym, Kaztalovka, and Baiterek districts," the specialist added.
Among the problem areas was the suburban village of Melovye Gorki near Uralsk, where residents suffered from power outages during any precipitation. Local resident Nina Donskova spoke about the situation:
"I have lived in this village for over 50 years. And I want to tell you that electricity here was very bad. Wind blows – lights go out. Snow falls – lights go out. Rain falls – lights go out. But now, thank you very much! They installed new poles for us, laid new, whatever they are called, wires or cables. They installed new transformers, beautiful, neat. Thank you very much for this. Everything is good with our power supply."
For next year, West Kazakhstan Region plans 16 more projects worth 33 billion tenge, aiming to reduce network wear to 11 percent by 2029. The issue of energy dependence in the Zhanibek and Bokey Orda districts, which import power from a neighboring country, is also being addressed: a combined 5 MW gas piston and solar plant will be launched there in early December.
"We adopted the 'Energy Independence in the Region' program 25 years ago. Our region was the most power-deficient at one time. A lot has been done, but one issue remained. These are two districts – Zhanibek and Bokey Orda. In a few days, we will commission a combined 5 MW station – gas piston and solar," emphasized Yakhiya Chudrov, honored power engineer of Kazakhstan and the CIS.
Comments