Kazakhstan updates construction approval and permitting rules
Kazakhstan has updated its rules for urban development and permitting procedures in the construction sector, NewsAsia.kz reports, citing Zakon.kz.

Kazakhstan has updated its rules for urban development and permitting procedures in the construction sector, NewsAsia.kz reports, citing Zakon.kz. The revised regulations establish a clear sequence of construction stages and conditions for issuing permit documentation.
Under the updated rules, the implementation of construction projects is carried out based on land plot rights and includes five key stages: obtaining baseline materials, developing and approving a preliminary design, drafting design and estimate documentation with comprehensive non-departmental expert review, notifying state architectural and construction control authorities of the start of construction and installation work, and subsequent acceptance and commissioning of the facility.
A simplified procedure is provided for certain categories. In particular, the reconstruction of individual residential houses up to two stories high (without allocating additional land and preserving the number of floors) and facilities covered by paragraph 4 of Article 98 of the relevant code are carried out solely based on a preliminary design. For such structures, there is no need to develop a full construction design, undergo expert review, or notify supervisory authorities. The exception is work in areas with high seismic hazard, as well as in risk zones for mudflows, landslides, and avalanches.
The public service "Provision of baseline materials for the development of construction and reconstruction (redevelopment, re-equipment, and repurposing) projects" is provided by the local administrations (akimats) of the capital, cities of republican and regional significance, and districts. Applications are registered on the day of receipt by the ACS GGC information system. If an application is submitted less than two hours before the end of the working day or during non-working hours, the period is calculated from the next working day.
The service provider is given two working days to verify the completeness of the document package. If inaccuracies or an incomplete set are identified, the applicant is granted three working days via a digital waiting list to rectify the remarks, which are not included in the total service delivery timeframe. If deficiencies are corrected on time, the acceptance date is considered the day of the initial application; otherwise, a refusal follows.
Materials are checked for compliance with approved master plans of settlements and detailed planning projects. In the absence of a master plan, development scheme, or detailed planning project, the issuance of baseline materials is not permitted.
In addition, grounds for suspending the procedure have been regulated: the death or incapacity of the applicant, waiting for a court act or decision of state bodies, correcting errors in documents, and the occurrence of force majeure circumstances — industrial and natural emergencies or a state of emergency.