Kazakhstan introduces new rules for connecting properties to gas grid

Kazakhstan has approved detailed procedures for connecting consumers to gas distribution networks, NewsAsia.kz reports, citing Zakon.kz.

Kazakhstan introduces new rules for connecting properties to gas grid
Photo: Zakon.kz

Kazakhstan has approved detailed procedures for connecting consumers to gas distribution networks, NewsAsia.kz reports, citing Zakon.kz. The technological connection process, network upgrades in the absence of spare capacity, and modifications to technical schemes will be carried out by gas distribution companies at the applicants' expense.

Individuals and legal entities seeking connection to the infrastructure will have to follow a regulated procedure. In the initial stage, an applicant applies to a gas distribution company for technical specifications. Following the review of submitted documents, the organization either issues the specifications or provides a reasoned refusal. Once approved, the consumer independently hires a licensed contractor to design the project and carry out construction and installation work.

Upon completion of construction, the applicant submits a notice along with a package of documentation. Household consumers must provide a gas supply design project, equipment data sheets, acceptance and inspection certificates for ventilation ducts and chimneys, a pipeline construction passport, and a technical maintenance agreement. Other consumer categories must additionally provide an order appointing a person responsible for safe operation and readiness documents for gas delivery in technically complex facilities.

Within two working days of receiving the request, the gas distribution company verifies the network's readiness and its compliance with the technical specifications. The physical connection is carried out within three working days at the consumer's expense, accompanied by connection certificates, boundary delineation records, and the sealing of gas meters. Agreements with household consumers take effect upon the first actual gas flow, while non-household consumers must sign an agreement before the tie-in begins.

Unauthorized connections without technical specifications and a gas supply contract will result in service suspension. The new rules and approved document templates will come into force on January 27, 2026.