Broken Detours, Crash Risks, and Missed Deadlines: Aktobe Region Residents Raise Concerns Over Highway Repairs
Official documents and public appeals target responsible agencies and contractors over delayed repairs along the Orsk highway, NewsAsia.kz reports, citing NUR.kz and the Diapazon newspaper.

Official appeals and public statements from local residents target contractors and road services carrying out reconstruction work from the Bekkul Baba residential area to the new bridge on the Orsk highway, NewsAsia.kz reports, citing NUR.kz and regional publication Diapazon. Villagers are raising alarms over the condition of temporary detour routes used daily by school buses and private vehicles.
📌 Delayed repairs and winter fears
According to the applicants, repair work began back in late July 2026, but the pace has drawn strong criticism from the local population. Residents state that the road surface was completely torn up, while key sections remain unfinished ahead of the winter season.
«We commute to the city for work every morning, and our children study in the city. The road has been completely torn apart. They started repairs at the end of July and, naturally, are running behind schedule. This road is very dangerous in winter. The bypasses around the bridges have no surfacing at all; in winter, not a single heavy-duty truck will make it through there. There are steep descents and sharp turns, and cars will spin off the road. This section is dangerous to human life and health. Trucks should not be allowed through before 10:00 AM at all, and firm deadlines are definitely needed. We fear for our children,» outraged residents were quoted as saying.
⚠️ National company's stance
In response to growing dissatisfaction, JSC NC KazAvtoZhol commented on the situation. According to official data, a contract for the reconstruction of the section from kilometer 763 to 791 of the Aktobe – Karabutak – Ulgaysyn highway was signed in May with contractor ASSANA-DorStroy LLP. The national company said that construction began in June 2026, with the full completion of the major project scheduled for 2029.
The agency explained that plans include upgrading the highway from technical Category III to Category I, demolishing old bridges, and building interchanges. Officials attributed the emergence of potholes and the deterioration of temporary bypasses to weather factors and heavy traffic from trucks carrying high axle loads.
⚖️ Warnings to the contractor
The editorial team does not yet have independent verification of all circumstances stated by the parties. NC KazAvtoZhol emphasized that official notices were issued to the builders: ASSANA-DorStroy LLP has been instructed to grade the roadbed, promptly eliminate surface irregularities, and implement additional measures to ensure safe travel for vehicles during the upcoming winter season.